Bags or a truck? Where ready-mix starts beating 80-lb bags

Every slab project hits the same fork: mix bags yourself or order a truck. The honest answer is a number, not a vibe — and it’s lower than most people think.

An 80-lb bag yields about 0.6 cu ft. A 10×10 pad at 4 inches needs 33.3 cu ft — that’s 56 bags, roughly 4,500 lb of material you’ll lift twice, and about 28 wheelbarrow trips of mixed concrete before any of it starts to set.

Cost crossover — bags vs ready-mix truckEST. 2026 US AVG
COST $CUBIC YARDS0123BAGS + MIXER RENTALTRUCK (SHORT-LOAD FEE INCLUDED)CROSSOVER ≈ 1.5 CU YD

Under a cubic yard, bags win on price and flexibility. Past about 1.5 cu yd, the truck wins even with a short-load fee — and it wins on quality too, because one consistent pour beats 56 slightly different batches.

Run your own numbers
The concrete slab calculator gives yards, bags, and cost side by side.
Concrete slab calculator →

Three things tip the math further toward the truck: any slab thicker than 4 inches, any pour you can’t finish in two hours, and any site where the mixer sits more than 50 feet from the forms.